Blown film line installation

A customer had purchased a new blown film line from Macchi in Italy. Concentric Engineered Solutions was asked to project manage the assembly and installation, in particular the assembly of the 14m tower prior to the arrival of the Macchi commissioning engineer. This involved removing sections of the factory roof and lifting the upper section of the tower with a 170 tonne mobile crane and then sliding the lower section underneath. Once the lower section was in the correct place, the upper section was craned into position and the two sections bolted together.

This project was completed in conjunction with Machinery Relocations Limited and Matched Limited.